Commissioning an electron microscope: the acceptance tests to witness

What to insist on seeing before signing the installation report, from the low voltage resolution figure through to the drift and contamination checks, and why your negotiating position disappears the moment the form is signed.

The installation engineer finishes, prints a report and asks for a signature. The person holding the pen is often a departmental head who was not in the room for the tests, and the tests were the point of the visit. Once that form is signed the warranty clock starts, and every remaining question becomes a service request rather than an obligation. Acceptance is the last moment when the supplier has to prove the instrument meets the contract.

Before the engineer arrives

Most failed commissioning visits fail on site readiness, not on the instrument.

The resolution test, and how it can be gamed

Resolution is quoted at a stated accelerating voltage and a stated working distance. Both conditions matter, and a resolution image taken at a different working distance or a different voltage from the one in the contract does not demonstrate the specification.

The tests people skip

Resolution gets witnessed because it is in the brochure. The tests that predict day to day usability are usually left out.

What the handover document must contain

Sign when the tests are done and the documents are complete, and not before. A supplier who has not yet been paid the final instalment answers the telephone.