Skip to main content

Solar Net-Metering in Bangladesh: The 2026 Guide for Industries, Universities & Hospitals

How net-metering works under the SREDA 2018 guideline (revised in 2025), what mills, factories, hospitals and universities in Bangladesh need to size a rooftop plant, payback maths, and a step-by-step approval flow with DPDC, DESCO, REB, BPDB and NESCO.

Bangladesh imports a meaningful share of its primary energy and the industrial tariff for medium-voltage consumers has steadily climbed since 2022. For mills, hospitals and universities with a usable roof, an on-grid net-metering solar system is now the most reliable way to lock in electricity costs for the next 25 years. This guide explains how the scheme works in 2026, what to size, how the maths play out, and the exact approval steps with the relevant utility (DPDC, DESCO, REB, BPDB or NESCO).

What net-metering actually is

Under the Net Metering Guidelines 2025 (Power Division, administered by SREDA), eligible consumers — both single-phase and three-phase — can install rooftop solar of up to 100% of their sanctioned load (80% of transformer capacity for MV consumers) and feed surplus generation back into the grid. The utility nets imported and exported energy on the bill, and any surplus at the end of the financial year is settled at the prevailing BERC bulk-purchase rate. The customer keeps a single bi-directional meter and the same connection — no separate license is required.

Sizing rule of thumb for Bangladesh

Bangladesh's mid-latitude climate produces roughly 105 kWh per kWp per month on a well-oriented south-facing tilt, with monocrystalline modules from Tier-1 OEMs. A clean rule of thumb: every 1,000 sq ft of usable, shadow-free roof can host about 13 kWp of PV. The table below shows how that scales for typical Bangladesh facilities.

Facility typeUsable roofPlant sizeYearly generationYearly bill saving (BDT 10/kWh)
Garments factory60,000 sq ft780 kWp9,82,800 kWhBDT 98,28,000
Jute / textile mill45,000 sq ft585 kWp7,37,100 kWhBDT 73,71,000
Tertiary hospital30,000 sq ft390 kWp4,91,400 kWhBDT 49,14,000
University block20,000 sq ft260 kWp3,27,600 kWhBDT 32,76,000
Cold-storage shed100,000 sq ft1,300 kWp16,38,000 kWhBDT 1,63,80,000

These are first-pass numbers — the real design must account for sanctioned load, transformer rating, roof orientation, shading, structural capacity (PSC vs corrugated metal), and the local utility's transformer headroom. Vvon's engineers run a full SLD plus structural and shadow analysis before quoting capacity.

What the payback actually looks like

On a typical industrial rooftop project in Bangladesh, the levelised cost of solar electricity is now well below the medium-voltage industrial tariff. The two flagship case studies Vvon engineered in the last three years illustrate the range:

Case studyCapacityYearly generationYearly savingROICO₂ reduction
Akij Agro Feed Ltd. (Narayanganj)1,503 KWp18,96,660 kWhBDT 2,01,04,500≈ 3.5 years1,150 t / yr
Ahad Jute Mills Ltd. (Jashore)575 KWp7,31,500 kWhBDT 77,54,000≈ 4 years445 t / yr

Beyond payback, the residual life of a Tier-1 PV plant is 25–30 years — meaning roughly two decades of effectively-free electricity once the capital is recovered. That is why net-metering has become the default capex decision for Bangladesh's larger industrial groups.

Step-by-step approval flow

  1. Feasibility & sizing study — roof survey, structural load check, shadow analysis, single-line diagram (SLD).
  2. Customer signs the SREDA-format application form and submits it to the relevant utility (DPDC / DESCO / BPDB / REB / NESCO) along with the SLD and equipment datasheets.
  3. Utility's technical committee inspects the site and approves the application in principle.
  4. EPC contractor (Vvon) procures Tier-1 modules, inverters and BoS, completes the structural and electrical installation.
  5. Utility installs a bi-directional meter and conducts a commissioning test.
  6. Net-metering agreement is signed; export/import accounting begins from the next billing cycle.

What to ask before you sign an EPC contract

How Vvon delivers

Vvon Technologies Limited has delivered 7+ MWp of industrial rooftop solar across Bangladesh, including the 1,503 KWp Akij Agro Feed plant in Narayanganj and the 575 KWp Ahad Jute Mills plant in Jashore. We are an authorized partner of Jinko Solar, Canadian Solar, JA Solar, Solis, Growatt, Sunways, Huawei and Schneider Electric — and we run an in-house engineering, EPC and O&M team based in Baridhara, Dhaka.

If you are evaluating a rooftop solar project, send us your last 12 months of electricity bills and a satellite image of your roof, and we will return a free indicative sizing and bill-saving estimate within five working days. Talk to an engineer →

Back to all Insights